Skip to main content

If you can read this text, your browser is not interpreting this page as the designers intended. This may be because you are using an obsolete, non-standards compliant browser or you have Cascading Style Sheets disabled.Read more about Web Standards at Reactive.

Major Projects

 

Project: VICTORIAN DESALINATION PROJECT
Contractor: THIESS DEGREMONT
Olex is supplying approximately $43m of high voltage underground cable for Australia's largest seawater desalination plant.

PROJECT: WIND FARM CABLING PROJECTS
Olex has supplied cabling solutions to numerous wind farm projects over the past few years, including Hallett (South Australia), Snowtown (South Australia), Capital (ACT), Clements Gap (South Australia) and Oaklands Hill (South Australia).

Project: RAPID GROWTH PROJECT 5 & 6, QUANTUM 1 & 2 
Contractor: FAST JOINT VENTURE
Olex is supplying approximately $25m of cables over 4 years for the above projects at BHP Billiton’s Iron Ore mine in Western Australia.

Project: RAPID GROWTH PROJECT 3 & 4 
Contractor: MARINE & PORTS DEVELOPMENT JOINT VENTURE
Olex is supplying approximately $5m of high voltage and extra high voltage cables for the Rapid Growth Project 3 (RGP3) and approximately $4m of cable for Rapid Growth Project 4 (RGP4) at BHP Billiton’s Iron Ore mine in Western Australia.

Project: MELBOURNE CONVENTION CENTRE
Contractor: ELECRAFT
Olex supplied approximately $2.5m of cable for the new Melbourne Convention Centre and Hilton Hotel Complex.

Project: GREATER COLOMBO GRID SUBSTATION PROJECT
Olex completed this major turnkey project in Colombo, Sri Lanka. The design and build project was to extend the 132kV power supply system and optical fibre comunication system in the Colombo area. Olex supplied almost 80km of high voltage cable for the project, which was completed in early 2006.